Starting March 17 the City of Hamilton will begin roadwork on Wilson Street and Sherman Avenue in Ward 3. The work will be completed in stages and is expected to last until December.

What to expect

  • Partial closures throughout the project will limit traffic to fewer lanes, but the road will remain open.
  • Full road closures will happen one section at a time as work progresses.
  • Detours will be posted to help drivers navigate around construction zones.
  • HSR buses will detour during this work.
  • Emergency services and their accessibility to residents will not be impacted.

Wilson Street work

  • Wentworth Street North to Sanford Avenue North: Full closure starts March 17 and is expected to be completed by mid-June.
  • Sanford Avenue North to Stirton Street: Work will begin mid-June and is expected to be completed by August.
  • Stirton Street to Chestnut Avenue: Work starts in August and is expected to be completed by October.

The work includes installing new watermains and sewers, reconstructing the road and converting traffic flow from one-way to two-way with associated traffic signals and intersection improvements

Additional work between Victoria Avenue and Wentworth Street will take place from April to May, including repaving the road, converting traffic flow from one-way to two-way with associated traffic signals and intersection improvements, adding a pedestrian crossing at Emerald Street North and replacing sidewalks at intersections

Sherman Avenue work

  • Cannon Street to Burlington Street: Work will begin mid-May and is expected to be completed by mid-June. The works will include repaving the road, repairing concrete and converting traffic flow from one-way to two-way with associated traffic signals and intersection improvements
  • Wilson Street to Cannon Street: Work will begin in October and is expected to be completed by December. The City will replace underground water pipes and sewers, rebuild the road and convert traffic flow from one-way to two-way with associated traffic signals and add intersection improvements.